A single-story house in West Seattle got a new steep roof with a 320 sq ft loft under it: a family room and an office, reached by a spiral stair from a double-height great room. The main floor was rebuilt at the same time, with a new kitchen, bath, windows, siding and porch. Permitted by Seattle SDCI and built by Evercrest without adding a square foot to the footprint.

The owners of a 1,180 sq ft single-story house on a sloped West Seattle lot needed a family room and a place to work, and did not want to give up the garden. The answer was to go up: take off the old roof, frame a 12/12 gable in its place and build a 320 sq ft loft inside it.
The loft holds a 203 sq ft family room and a 114 sq ft office. Below it, the front of the house became one great room open to the ridge, with a spiral stair up to the loft. Since the house was open to the studs anyway, the main floor was rebuilt in the same run: a new kitchen, a new bath, new windows, siding, floors and a longer front porch.
On the left, July 2026: the new gable sheathed, the loft window openings cut, the porch roof going on. On the right, November 2026: the same front finished, with siding, windows, the porch and the garden back in place. Drag the handle to compare.

beforeafterDrag to compare the east elevation from the permit set with the finished front: the same 12/12 roof line, the same porch with its flat roof, the same entry and steps. One thing changed on site: the loft window was built taller than drawn.


The site was filmed on July 13, 2026, with the framing up, and photographed again in November when the house was finished. The bathroom is the one room caught before any work: the original, on its last day. Tap any photo to enlarge.








Six frames from the framing stage, before insulation and drywall. Tap any photo to enlarge.






The great room, the kitchen, two bedrooms, the bath, a den and the back hall on the main floor; the family room and the office in the loft. Room sizes are from the permit drawings. Tap any room to enlarge.







The front of the house is now one room for living and dining, with the ceiling following the new roof up to the ridge and tall windows in the gable. A wide sliding door opens to the porch. The spiral stair, black steel with wood treads, stands at the edge of the room and climbs to the loft railing, so the floor stays open.



Flat-panel wood cabinets run to the ceiling around three sides, under white counters and a backsplash of green tile set vertically. A peninsula with seating faces the great room. The appliances are stainless: a double-oven range, a microwave above it, a dishwasher, a French-door refrigerator and an apron-front sink under the pass-through window.



Everything on this level is new. The 203 sq ft family room sits under the roof slopes with the gable window and its view in front and a railing over the great room. A glazed door leads to the 114 sq ft office with a window in the rear gable. A ductless heat pump heats and cools the level, and a ceiling fan moves the air under the ridge.



The bath is all new: a terracotta hexagon floor, a white vessel sink on a wood vanity with a brass faucet, a dark green built-in for linens, and a tub tiled to the top with black fixtures. The main bedroom got new windows, a wood accent wall behind the bed and a ceiling fan.


The rest of the finish photo shoot: the outside from every side, the porch, and every room on both levels. Tap any photo to enlarge.



































Adding a floor is a structural project first. A structural engineer drew the new load path from the ridge to the ground, and the existing house was reinforced to carry it: new concrete footings, posts and beams under the loft, hold-downs anchored into the existing foundation, old floor joists sistered, and new wall studs run continuous to the roof plate.








The house stands on a 5,571 sq ft lot in the NR3 zone, on a slope with a view east over the city. Part of the lot is mapped as a steep-slope area, so the permit included an environmental review before the city signed off. The site plan carries the note that decided the design: existing home, no changes to footprint. The garage, the carport, the driveway and the garden stayed where they were.


On a small city lot, a second-story addition or a loft under a new roof is often the only way to add living space: setbacks, lot coverage and the garden leave no room to build out. This West Seattle home addition went from 1,180 to 1,500 finished sq ft on the footprint it already had. Evercrest built all of it under one Seattle SDCI permit that included a steep-slope review: the structural work, the new roof, the loft and the remodel of the main floor.
Planning a second-story addition, an attic or loft conversion, a dormer or a whole-home remodel in West Seattle, Seattle or on the Eastside? The numbers on this page come from a finished project: $410,340 and 5.5 months of construction. A free on-site visit tells you what your house and your lot allow, and what your addition would cost.
What the finished house shows, from the siding to the tile.
Every addition starts with the same doubts. Here is how this project answered each one.
Yes. This house kept its footprint to the inch: the lot coverage did not change. The old low roof came off, a new 12/12 gable roof went on, and the space under it became a 320 sq ft loft with a family room and an office. Finished area went from 1,180 to 1,500 sq ft.
It has to be checked, and here it was. A structural engineer reviewed the existing foundation and framing. We poured new concrete footings where the new posts land, anchored hold-downs into the existing stem wall, sistered the old floor joists and ran the new wall studs continuous up to the roof plate.
The lot is zoned NR3, which allows 30 feet. The new ridge sits at 27 feet 1 inch, so the steep roof and the loft fit under the limit with room to spare.
Because it takes a fraction of the floor a straight stair needs. The stair stands on its own beam and footing at the edge of the great room and lands on a steel-framed landing at the loft, so the main floor stays open.
Two stages. The Seattle SDCI permit took five months, from the application on May 6 to the permit on October 6, 2025, including a steep-slope review of the lot. Construction then took 5.5 months, and the final inspection passed on November 3, 2026.
This one was $410,340: the new roof and loft, the structural work under them, new windows and siding, a new kitchen and bath, floors, the porch and every finish in the house. It is a real number from a finished project, not an estimate.
A free on-site review gives you the real numbers for your house: structure, zoning, height, permits, timeline and a price range, before you commit to anything.